Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Longest duration Highest cost slope Least cost slope Shortest duration Longest duration Highest cost slope Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 15 20 25 35 15 20 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 1 4 2 3 1 4 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 1 0.999 0.5 0.841 1 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP