Construction Planning and Management Which one of the following represents an event? Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Interfering float Total float Free float Duration Interfering float Total float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of construction materials Site survey All listed here Availability of labour Availability of construction materials Site survey All listed here Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel Hoe Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP