Construction Planning and Management Which one of the following represents an event? Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Crosses Dots Horizontal lines Vertical lines Crosses Dots Horizontal lines ANSWER DOWNLOAD EXAMIANS APP