Construction Planning and Management Which one of the following represents an event? Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Normal distribution curve Poisson's distribution curve None of these Beta distribution curve Normal distribution curve Poisson's distribution curve None of these Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Modified Mile stone chart Bar chart Gantt chart All listed here Modified Mile stone chart Bar chart Gantt chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site 50% at the site and 50% under procurement 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP