Construction Planning and Management Which one of the following represents an event? Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Crash time Between normal time and crash time Normal time Optimistic time Crash time Between normal time and crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Major projects Any project Minor projects All listed here Major projects Any project Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 250 kg Reduce by 200 kg Increase by 250 kg Increase by 200 kg Reduce by 250 kg Reduce by 200 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP