Construction Planning and Management Which one of the following represents an event? Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Extraordinary delay in communications Top level executions over work Rigid structure All listed here Extraordinary delay in communications Top level executions over work Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Event Float Constraint Duration Event Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 10 days 16 days 4 days 6 days 10 days 16 days 4 days ANSWER DOWNLOAD EXAMIANS APP