Construction Planning and Management Which one of the following represents an event? Plastering of walls Selecting sites Concrete cured Fixing of door Plastering of walls Selecting sites Concrete cured Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Line organization Line and staff organization Functional organization Effective organization Line organization Line and staff organization Functional organization Effective organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 2 1 3 4 2 1 3 ANSWER DOWNLOAD EXAMIANS APP