Construction Planning and Management Which one of the following represents an event? Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Longest duration Shortest duration Least cost slope Highest cost slope Longest duration Shortest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D All listed here LS = LF - D EF = ES + D LF = LS + D All listed here LS = LF - D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications Rigid structure Top level executions over work All listed here Extraordinary delay in communications Rigid structure Top level executions over work All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Synthesising in concepts Is based on time estimate All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate All listed here Is built of activities oriented programme ANSWER DOWNLOAD EXAMIANS APP