Construction Planning and Management Which one of the following represents an event? Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Vibration Tamping Kneading Pressing Vibration Tamping Kneading Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 2.3% and 84.1% 97.7% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves All listed here Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves All listed here Having a single lump, are called uninodal curves If symmetrical, are called normal curves If not symmetrical, are called skew curves ANSWER DOWNLOAD EXAMIANS APP