Construction Planning and Management Which one of the following represents an event? Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 1000 kg 300 kg 900 kg 30 kg 1000 kg 300 kg 900 kg 30 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started All listed here Digging of foundation completed Laying of concrete started Digging of foundation started All listed here Digging of foundation completed Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 36 9 54 81 36 9 54 81 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Deterministic activities Large and complex projects Research and development projects Small projects Deterministic activities Large and complex projects Research and development projects Small projects ANSWER DOWNLOAD EXAMIANS APP