Construction Planning and Management Which one of the following represents an event? Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements ANSWER DOWNLOAD EXAMIANS APP