Construction Planning and Management Which one of the following represents an event? Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) All listed here CPP (Critical Path Plotted) CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site 50% at the site and 50% under procurement 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float Free float and independent float None of these Total float and independent float Total float and free float Free float and independent float None of these Total float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 1-2 is 4 All listed here ANSWER DOWNLOAD EXAMIANS APP