Construction Planning and Management Which one of the following represents an event? Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line organization None of these Line and staff organization Functional organization Line organization None of these Line and staff organization Functional organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing Activity of excavation which takes 8 units of time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 1 More than 50 % Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 ANSWER DOWNLOAD EXAMIANS APP