Construction Planning and Management Which one of the following represents an event? Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Bus starts from Jaipur Sessional work completed Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed Site investigation started Class is being attended ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Assistant Engineer Junior Engineer Engineer Executive Engineer Assistant Engineer Junior Engineer Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP