Construction Planning and Management Which one of the following represents an event? Plastering of walls Fixing of door Selecting sites Concrete cured Plastering of walls Fixing of door Selecting sites Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete Excavation for foundation Setting of question paper All listed here Curing of concrete Excavation for foundation Setting of question paper All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct (ii) and (iii) are correct (i) and (iii) are correct Only (i) is correct (i) and (ii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Beta distribution curve None of these Poisson's distribution curve Normal distribution curve Beta distribution curve None of these Poisson's distribution curve Normal distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Wet sticky clay Moist loam Good common earth Sand and gravel Wet sticky clay Moist loam Good common earth Sand and gravel ANSWER DOWNLOAD EXAMIANS APP