Construction Planning and Management Which one of the following represents an event? Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be More than X Less than X Equal to X Any of the above More than X Less than X Equal to X Any of the above ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP