Construction Planning and Management Which one of the following represents an event? Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is All listed here A person An agency A firm All listed here A person An agency A firm ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method All listed here Provides a realistic approach to daily problems Avoids delays which are very common in bar charts Is an improvement upon bar chart method All listed here Provides a realistic approach to daily problems Avoids delays which are very common in bar charts Is an improvement upon bar chart method ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 20 35 15 25 20 35 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Wet sticky clay Good common earth Moist loam Well blasted rock Wet sticky clay Good common earth Moist loam Well blasted rock ANSWER DOWNLOAD EXAMIANS APP