Construction Planning and Management Which one of the following represents an event? Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Extraordinary delay in communications Top level executions over work Rigid structure All listed here Extraordinary delay in communications Top level executions over work Rigid structure All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Event flow scheduling technique Critical ratio scheduling Slotting technique for scheduling Short interval scheduling Event flow scheduling technique Critical ratio scheduling Slotting technique for scheduling Short interval scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope Longest duration ANSWER DOWNLOAD EXAMIANS APP