Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LS = LF - D All listed here LF = LS + D EF = ES + D LS = LF - D All listed here LF = LS + D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Increase of project completion time Change of critical path Decrease of project completion time All of these Increase of project completion time Change of critical path Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Connector All listed here Event Node Connector All listed here Event Node ANSWER DOWNLOAD EXAMIANS APP