Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good EF = ES + D All listed here LF = LS + D LS = LF - D EF = ES + D All listed here LF = LS + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Vibration Tamping Kneading Pressing Vibration Tamping Kneading Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Free float Interfering float Total float Duration Free float Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP