Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest May be shortest May be longest Is always longest Is always shortest May be shortest May be longest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Minimum float Zero float None of these Maximum float Minimum float Zero float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Separation of planning and design part All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part All listed here Each individual maintains functional efficiency Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP