Construction Planning and Management
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is correct
A is correct but R is not correct
Both A and R is incorrect
R is correct but A is not correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost

ANSWER DOWNLOAD EXAMIANS APP