Construction Planning and Management
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is incorrect
Both A and R is correct
A is correct but R is not correct
R is correct but A is not correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all activities
Normal durations for all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Weighing accurately, the quantity of each material for a job before mixing
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Controlling the total quantity at each batch
Controlling the quantity of each material into each batch

ANSWER DOWNLOAD EXAMIANS APP