Construction Planning and Management
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is correct
Both A and R is incorrect
R is correct but A is not correct
A is correct but R is not correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP