Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D All listed here EF = ES + D LS = LF - D LF = LS + D All listed here EF = ES + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources Preparation of estimates All listed here Preparation of specifications Initiating the procurement action of resources Preparation of estimates All listed here Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Selecting sites Fixing of door Concrete cured Plastering of walls Selecting sites Fixing of door Concrete cured Plastering of walls ANSWER DOWNLOAD EXAMIANS APP