Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct Both A and R is correct A is correct but R is not correct Both A and R is incorrect R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % More than 50 % 0.5 1 Less than 50 % More than 50 % 0.5 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 15 35 20 25 15 35 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest critical activity Cheapest noncritical activity Costliest noncritical activity Cheapest critical activity Costliest critical activity Cheapest noncritical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between None of these Total float and independent float Total float and free float Free float and independent float None of these Total float and independent float Total float and free float Free float and independent float ANSWER DOWNLOAD EXAMIANS APP