Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Dragline Shovel Hoe None of these Dragline Shovel Hoe None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time All listed here Most likely time Pessimistic time Optimistic time All listed here Most likely time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 36 54 81 9 36 54 ANSWER DOWNLOAD EXAMIANS APP