Construction Planning and Management
Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same

Both A and R is incorrect
A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Increase in rates of only important materials
Rate of inflation
Variation in total cost of the project on an ad hoc basis
Variation in cost in materials element, labour element and petrol-oil-lubricant element

ANSWER DOWNLOAD EXAMIANS APP