Construction Planning and Management
Total float for any activity is defined as the difference between

Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than latest event time of preceding node
less than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All listed here
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Normal durations for all the activities

ANSWER DOWNLOAD EXAMIANS APP