Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP