Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 9 days 8 days 15 days 10 days 9 days 8 days 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 Less than 50 % 1 More than 50 % 0.5 Less than 50 % 1 More than 50 % ANSWER DOWNLOAD EXAMIANS APP