Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document
For the payment of advances to labour and other staff

ANSWER DOWNLOAD EXAMIANS APP