Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project B
should invest in project A
could invest in either of the two projects
should invest in neither of the two projects

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in costs for the removal of defects
Reduction in wastage of inspection costs

ANSWER DOWNLOAD EXAMIANS APP