Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Event Float Duration Constraint Event Float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 8,75,000 Rs. 10,50,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 8,75,000 Rs. 10,50,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum cost Minimum time Maximum time Maximum cost Minimum cost Minimum time Maximum time Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Minimum Maximum Infinite Zero Minimum Maximum Infinite ANSWER DOWNLOAD EXAMIANS APP