Construction Planning and Management
Consider the following statements:In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.

1 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
2, 3 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP