Construction Planning and Management
Consider the following statements:In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.

1, 2 and 4 are correct
1, 2 and 3 are correct
2, 3 and 4 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest finish time and earliest start time for its successor activity
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time
Its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP