Construction Planning and Management
Consider the following statements:In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.

2, 3 and 4 are correct
1 and 4 are correct
1, 2 and 4 are correct
1, 2 and 3 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project B
should invest in project A
could invest in either of the two projects
should invest in neither of the two projects

ANSWER DOWNLOAD EXAMIANS APP