Construction Planning and Management PERT analysis is based on All listed here Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties Interdependencies of activities All of these Project progress Uncertainties Interdependencies of activities All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 2-3 is 7 1-2 is 4 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Class is being attended Site investigation started Bus starts from Jaipur Sessional work completed Class is being attended Site investigation started Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP