Construction Planning and Management PERT analysis is based on All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 4 days 6 days 10 days 16 days 4 days 6 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Selecting sites Fixing of door Plastering of walls Concrete cured Selecting sites Fixing of door Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Dummy Free float Constraint Event Dummy Free float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Crash time Standard time Slow time Normal time Crash time Standard time Slow time ANSWER DOWNLOAD EXAMIANS APP