Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 85 and 75 80 and 90 75 and 83 90 and 80 85 and 75 80 and 90 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Dots Horizontal lines Vertical lines Crosses Dots Horizontal lines Vertical lines Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Normal time Between normal time and crash time Crash time Optimistic time Normal time Between normal time and crash time Crash time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP