Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 85 and 75 90 and 80 80 and 90 75 and 83 85 and 75 90 and 80 80 and 90 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Zero Minimum Infinite Maximum Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Resources Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement 100% at the site 67% at the site and 33% under procurement 33% at the site and 67% under procurement 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 19 days 14 days 13 days 9 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP