Construction Planning and Management For the execution of a project, a contractor is An agency All listed here A firm A person An agency All listed here A firm A person ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 14 days 9 days 19 days 13 days 14 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Constraint Duration Float Event Constraint Duration Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer All listed here An architect An owner An engineer All listed here An architect An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP