Construction Planning and Management For the execution of a project, a contractor is A firm A person An agency All listed here A firm A person An agency All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 36 9 81 54 36 9 81 54 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Minimum cost Minimum time Maximum time Maximum cost Minimum cost Minimum time Maximum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time Optimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties All of these ANSWER DOWNLOAD EXAMIANS APP