Construction Planning and Management For the execution of a project, a contractor is An agency All listed here A firm A person An agency All listed here A firm A person ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Interfering float Duration Total float Free float Interfering float Duration Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Maximum cost Maximum time Minimum cost Minimum time Maximum cost Maximum time Minimum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP