Construction Planning and Management For the execution of a project, a contractor is All listed here A person A firm An agency All listed here A person A firm An agency ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Interfering float Total float Independent float Free float Interfering float Total float Independent float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only The particular activity involved Succeeding activities None of these Preceding activities The particular activity involved Succeeding activities None of these Preceding activities ANSWER DOWNLOAD EXAMIANS APP