Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate ANSWER DOWNLOAD EXAMIANS APP