Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Light construction Electrical construction Heavy construction Industrial construction Light construction Electrical construction Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float Zero float Maximum float None of these Minimum float Zero float Maximum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP