Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent The office area is being cleaned Foundation is being dug Site located The invitations are being sent The office area is being cleaned Foundation is being dug Site located ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Industrial construction Light construction Heavy construction Private construction Industrial construction Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 24 19 14 None of these 24 19 14 ANSWER DOWNLOAD EXAMIANS APP