Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
less than or equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Earliest finish of an activity is always

Less than earliest event time of the following node
Greater than or equal to earliest event time of the following node
Less than or equal to earliest event time of the following node
Greater than earliest event time of the following node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

All listed here
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

ANSWER DOWNLOAD EXAMIANS APP