Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Horizontal lines Vertical lines Dots Crosses Horizontal lines Vertical lines Dots ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Well blasted rock Moist loam Wet sticky clay Good common earth Well blasted rock Moist loam Wet sticky clay Good common earth ANSWER DOWNLOAD EXAMIANS APP