Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 12500 kg 22500 kg 5000 kg 10000 kg 12500 kg 22500 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration ANSWER DOWNLOAD EXAMIANS APP