Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float for any activity is defined as the difference between

its earliest finish time and latest start time for its successor activity
its earliest finish time and earliest start time for its successor activity
its latest finish time and earliest start time for its successor activity
its latest start time and earliest start time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP