Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Tampers Sheep foot rollers Vibratory rollers Smooth-wheeled rollers Tampers Sheep foot rollers Vibratory rollers Smooth-wheeled rollers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1920 1940 1930 1910 1920 1940 1930 1910 ANSWER DOWNLOAD EXAMIANS APP