Construction Planning and Management
In time-cost optimization of a project, crashing is done.

On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Only on activities lying on the original critical path and having flatter cost slopes
On all the activities lying on the critical path
On all the activities

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document
For the payment of advances to labour and other staff

ANSWER DOWNLOAD EXAMIANS APP