Construction Planning and Management
In PERT analysis, the time estimates of activities and probability of their occurrence follow

None of these
Beta distribution curve
Poisson's distribution curve
Normal distribution curve

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Establish priorities
Identify the activities which can be delayed without affecting the total float of preceding activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Controlling the total quantity at each batch

ANSWER DOWNLOAD EXAMIANS APP