Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Beta distribution curve Poisson's distribution curve Normal distribution curve None of these Beta distribution curve Poisson's distribution curve Normal distribution curve None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 None of these 19 14 24 None of these 19 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Shovel Dragline Hoe None of these Shovel Dragline Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP