Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve None of these Normal distribution curve Beta distribution curve Poisson's distribution curve None of these Normal distribution curve Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Constraint Dummy Free float Event Constraint Dummy Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Kneading Pressing Vibration Tamping Kneading Pressing Vibration Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 10 days 4 days 6 days 16 days 10 days 4 days 6 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 3.7 years 5 years 4.23 years 7.87 years 3.7 years 5 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Same Zero Negative Positive Same Zero Negative ANSWER DOWNLOAD EXAMIANS APP