Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow None of these Poisson's distribution curve Beta distribution curve Normal distribution curve None of these Poisson's distribution curve Beta distribution curve Normal distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates Initiating the procurement action of resources All listed here Preparation of specifications Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Bus starts from Jaipur Sessional work completed Class is being attended Site investigation started Bus starts from Jaipur Sessional work completed Class is being attended Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Interfering float Total float Independent float Free float Interfering float Total float Independent float ANSWER DOWNLOAD EXAMIANS APP