Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow None of these Beta distribution curve Poisson's distribution curve Normal distribution curve None of these Beta distribution curve Poisson's distribution curve Normal distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) All listed here MCE (Minimum Cost Expenditure) CPA (Critical Path Analysis) CPP (Critical Path Plotted) All listed here ANSWER DOWNLOAD EXAMIANS APP