Construction Planning and Management Which of the following is not a PERT event? Site investigation started Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started Sessional work completed Class is being attended Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Heavy construction Light construction None of these Industrial construction Heavy construction Light construction None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 2-3 is 7 3-4 is 8 All listed here 1-2 is 4 2-3 is 7 3-4 is 8 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Zero float None of these Minimum float Maximum float Zero float None of these Minimum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP