Construction Planning and Management Which of the following is not a PERT event? Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 1 0.5 More than 50 % Less than 50 % 1 0.5 More than 50 % ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Kneading Tamping Vibration Pressing Kneading Tamping Vibration ANSWER DOWNLOAD EXAMIANS APP