Construction Planning and Management Which of the following is not a PERT event? Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed Site investigation started Class is being attended Bus starts from Jaipur Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 25 20 15 35 25 20 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 30 kg/tonne 40 kg/tonne 20 kg/tonne 50 kg/tonne 30 kg/tonne 40 kg/tonne 20 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Event Dummy Free float Constraint Event Dummy Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Concrete Asphalt Loose sand Firm earth Concrete Asphalt Loose sand Firm earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP