Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started Sessional work completed Class is being attended Bus starts from Jaipur Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 Rs. 31050 Rs. 37950 Rs. 50000 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Same Zero Positive Negative Same Zero Positive ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Increase of project completion time All of these Decrease of project completion time Change of critical path Increase of project completion time All of these Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Survey of the site Initiation of proposal Preparation of estimate Preparation of tender Survey of the site Initiation of proposal Preparation of estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP