Construction Planning and Management Which of the following is not a PERT event? Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.5 0.841 0.999 1 0.5 0.841 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Normal time Crash time Optimistic time Between normal time and crash time Normal time Crash time Optimistic time Between normal time and crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Duration Float Constraint Event Duration Float Constraint ANSWER DOWNLOAD EXAMIANS APP