Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Crash time Normal time Optimistic time Between normal time and crash time Crash time Normal time Optimistic time Between normal time and crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP