Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Decrease of project completion time All of these Increase of project completion time Change of critical path Decrease of project completion time All of these Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Standard time Normal time Slow time Crash time Standard time Normal time Slow time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Negative Same Zero Positive Negative Same Zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Dragline Shovel Hoe None of these Dragline Shovel Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP