Construction Planning and Management Railway projects are treated as Light construction None of these Industrial construction Heavy construction Light construction None of these Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float None of these Maximum float Zero float Minimum float None of these Maximum float Zero float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Critical path scheduling Resource smoothening Updating Resource levelling Critical path scheduling Resource smoothening Updating ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP