Construction Planning and Management Railway projects are treated as Light construction Industrial construction None of these Heavy construction Light construction Industrial construction None of these Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Increasing the direct cost and indirect cost both Decreasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP