Construction Planning and Management Railway projects are treated as Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Free float Dummy Event Constraint Free float Dummy Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced Cost of project is controlled Uniform demand of resources is achieved Total duration of project is increased Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 8 days 10 days 15 days 9 days 8 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 3 2 1 4 3 2 1 ANSWER DOWNLOAD EXAMIANS APP