Construction Planning and Management Railway projects are treated as Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method Provides a realistic approach to daily problems All listed here Avoids delays which are very common in bar charts Is an improvement upon bar chart method ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 10 days 8 days 15 days 9 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP