Construction Planning and Management Railway projects are treated as Industrial construction Light construction None of these Heavy construction Industrial construction Light construction None of these Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Curing of concrete Excavation for foundation All listed here Setting of question paper Curing of concrete Excavation for foundation All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Engineer Assistant Engineer Junior Engineer Executive Engineer Engineer Assistant Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A person A firm All listed here An agency A person A firm All listed here ANSWER DOWNLOAD EXAMIANS APP