Construction Planning and Management Railway projects are treated as Industrial construction None of these Light construction Heavy construction Industrial construction None of these Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer Executive Engineer Assistant Engineer Chief Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A None of these expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 85 and 75 90 and 80 75 and 83 80 and 90 85 and 75 90 and 80 75 and 83 80 and 90 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time ANSWER DOWNLOAD EXAMIANS APP