Construction Planning and Management Railway projects are treated as Light construction Heavy construction None of these Industrial construction Light construction Heavy construction None of these Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 50 kg/tonne 40 kg/tonne 30 kg/tonne 20 kg/tonne 50 kg/tonne 40 kg/tonne 30 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect An owner All listed here An engineer An architect An owner All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 20.143 minutes 15 minutes 27 minutes 21 minutes 20.143 minutes 15 minutes 27 minutes ANSWER DOWNLOAD EXAMIANS APP