Construction Planning and Management Railway projects are treated as Light construction None of these Industrial construction Heavy construction Light construction None of these Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Each individual maintains functional efficiency Separation of planning and design part Strict adherence to specifications All listed here Each individual maintains functional efficiency Separation of planning and design part Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good All listed here LS = LF - D LF = LS + D EF = ES + D All listed here LS = LF - D LF = LS + D EF = ES + D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications ANSWER DOWNLOAD EXAMIANS APP