Construction Planning and Management Railway projects are treated as None of these Light construction Industrial construction Heavy construction None of these Light construction Industrial construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 19 days 9 days 13 days 14 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 15 days 8 days 9 days 10 days 15 days 8 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 1740 Rs. 5220 Rs. 3480 Rs. 6960 Rs. 1740 Rs. 5220 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Bus starts from Jaipur Class is being attended Sessional work completed Site investigation started Bus starts from Jaipur Class is being attended Sessional work completed Site investigation started ANSWER DOWNLOAD EXAMIANS APP