Construction Planning and Management Railway projects are treated as Light construction Heavy construction Industrial construction None of these Light construction Heavy construction Industrial construction None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 3480 Rs. 1740 Rs. 5220 Rs. 6960 Rs. 3480 Rs. 1740 Rs. 5220 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on All listed here Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP