Construction Planning and Management Critical path lies along the activities having total float Positive Zero Same Negative Positive Zero Same Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 3425 kg 4350 kg 5515 kg 2975 kg 3425 kg 4350 kg 5515 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Concrete Loose sand Ice Earth Concrete Loose sand Ice ANSWER DOWNLOAD EXAMIANS APP