Construction Planning and Management Critical path lies along the activities having total float Zero Positive Same Negative Zero Positive Same Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency All listed here A person A firm An agency All listed here A person A firm ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Standard time Crash time Normal time Optimistic time Standard time Crash time Normal time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is Is based on time estimate All listed here Is built of activities oriented programme Synthesising in concepts Is based on time estimate All listed here Is built of activities oriented programme Synthesising in concepts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 1, 3 and 4 1, 2 and 5 1, 2 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP