Construction Planning and Management

Construction Planning and Management
Critical path lies along the activities having total float

Positive
Zero
Same
Negative

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

Free float
Interfering float
Total float
Duration

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The time with which direct cost does not reduce with the increase in time is known as

Crash time
Standard time
Optimistic time
Normal time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
PERT analysis is based on

Optimistic time
Most likely time
All listed here
Pessimistic time

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The object of technical planning, is

Initiating the procurement action of resources
Preparation of specifications
All listed here
Preparation of estimates

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be

Less than X
Equal to X
More than X
Any of the above

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑