Construction Planning and Management Critical path May be longest Is always longest May be shortest Is always shortest May be longest Is always longest May be shortest Is always shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Slow time Standard time Normal time Crash time Slow time Standard time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 15 35 25 20 15 35 25 20 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete All listed here Setting of question paper Excavation for foundation Curing of concrete All listed here Setting of question paper Excavation for foundation ANSWER DOWNLOAD EXAMIANS APP