Construction Planning and Management Critical path Is always longest Is always shortest May be longest May be shortest Is always longest Is always shortest May be longest May be shortest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 9 days 14 days 13 days 19 days 9 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has None of these Minimum float Zero float Maximum float None of these Minimum float Zero float Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % 0.5 1 More than 50 % Less than 50 % 0.5 1 More than 50 % ANSWER DOWNLOAD EXAMIANS APP