Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of

1, 3 and 4
3, 4 and 5
1, 2 and 5
1, 2 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

A part of the money kept in reserve for providing additional structures and structural modifications
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes