Construction Planning and Management
Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of

1, 3 and 4
1, 2 and 4
1, 2 and 5
3, 4 and 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel.

(i), (ii) and (iv) are correct
(i) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct

ANSWER DOWNLOAD EXAMIANS APP