Construction Planning and Management
Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of

1, 2 and 4
3, 4 and 5
1, 2 and 5
1, 3 and 4

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The several alternatives of the project that have been considered
The contract documents for inviting tenders
The detailed estimated cost based on detailed design
The soil survey, traffic survey, concept design and approximate cost

ANSWER DOWNLOAD EXAMIANS APP