Construction Planning and Management Frequency distribution curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves All listed here If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.999 0.5 0.841 1 0.999 0.5 0.841 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 4350 kg 3425 kg 5515 kg 2975 kg 4350 kg 3425 kg 5515 kg 2975 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Succeeding activities None of these The particular activity involved Preceding activities Succeeding activities None of these The particular activity involved Preceding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than or equal to earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP