Construction Planning and Management Frequency distribution curves If symmetrical, are called normal curves Having a single lump, are called uninodal curves If not symmetrical, are called skew curves All listed here If symmetrical, are called normal curves Having a single lump, are called uninodal curves If not symmetrical, are called skew curves All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements No, because of savings in site labour Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of repetitive manufacture of a number of elements ANSWER DOWNLOAD EXAMIANS APP