Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be Less than 50 % More than 50 % 1 0.5 Less than 50 % More than 50 % 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time All listed here Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established Net work is drawn by connecting the activities and the events All listed here A project is divided into various activities Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority All listed here Unity of command Effective control at all levels Delegation of authority All listed here Unity of command Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP