Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B None of these expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1910 1920 1930 1940 1910 1920 1930 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Positive Same Negative Zero Positive Same Negative ANSWER DOWNLOAD EXAMIANS APP