Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Effective organization Line and staff organization Line organization Functional organization Effective organization Line and staff organization Line organization Functional organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Decrease of project completion time Increase of project completion time Change of critical path All of these Decrease of project completion time Increase of project completion time Change of critical path All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered The contract documents for inviting tenders The soil survey, traffic survey, concept design and approximate cost The detailed estimated cost based on detailed design The several alternatives of the project that have been considered ANSWER DOWNLOAD EXAMIANS APP