Construction Planning and Management In the given figure, the network of a project represents Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of an excavation of a footing None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss Change in output due to change in input Comparison of assets and liabilities Economics of cost and benefits of the project Comparison of profit and loss Change in output due to change in input ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 14 days 13 days 9 days 19 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Normal time Optimistic time Standard time Crash time Normal time Optimistic time Standard time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Asphalt Loose sand Concrete Firm earth Asphalt Loose sand Concrete Firm earth ANSWER DOWNLOAD EXAMIANS APP