Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known Connector Event Node All listed here Connector Event Node All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Digging of foundation started Digging of foundation completed Laying of concrete started All listed here Digging of foundation started Digging of foundation completed Laying of concrete started All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between None of these Total float and free float Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities, which can be delayed without affecting the total float of succeeding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 13 days 9 days 14 days 19 days 13 days 9 days ANSWER DOWNLOAD EXAMIANS APP