Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities Only on activities lying on the original critical path and having flatter cost slopes On all the activities lying on the critical path ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent Foundation is being dug Site located The office area is being cleaned The invitations are being sent Foundation is being dug Site located The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 5,000 Rs. 7,600 Rs. 8,800 Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 Rs. 6,400 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Shortest duration Longest duration Least cost slope Highest cost slope Shortest duration Longest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP