Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Zero Positive Negative Same Zero Positive Negative Same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Interdependencies of activities Uncertainties All of these Project progress Interdependencies of activities Uncertainties All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 10 days 8 days 9 days 15 days 10 days 8 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? The invitations are being sent Site located The office area is being cleaned Foundation is being dug The invitations are being sent Site located The office area is being cleaned Foundation is being dug ANSWER DOWNLOAD EXAMIANS APP