Construction Planning and Management In the given figure, the network of a project represents None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing None of these Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Number of operations All listed here Output of labour Output of machinery Number of operations All listed here Output of labour Output of machinery ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 Rs. 31050 Rs. 50000 Rs. 34500 Rs. 37950 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 50 kg/tonne 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne 20 kg/tonne 30 kg/tonne ANSWER DOWNLOAD EXAMIANS APP