Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing Activity of an excavation which starts at event No. 1 and ends at even No. 2 Activity of excavation which takes 8 units of time None of these Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Event Float Constraint Duration Event Float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 3.5 and 5/6 5 and 25/36 3.5 and 25/36 4 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP