Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 9 days 15 days 8 days 10 days 9 days 15 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct Both A and R is incorrect A is correct but R is not correct R is correct but A is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP