Construction Planning and Management
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

4350 kg
5515 kg
2975 kg
3425 kg

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The detailed estimated cost based on detailed design
The contract documents for inviting tenders
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

On all the activities lying on the critical path
On all the activities
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Only on activities lying on the original critical path and having flatter cost slopes

ANSWER DOWNLOAD EXAMIANS APP