Construction Planning and Management
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is

3425 kg
5515 kg
2975 kg
4350 kg

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

All listed here
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP