Construction Planning and Management
Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is

1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 3, 4, 2, 5
1, 2, 3, 4, 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

Yes, because of the very high order of quality control for the factory made components
No, because of savings in site labour
No, because of repetitive manufacture of a number of elements
Yes, because of heavier overheads and handling cost

ANSWER DOWNLOAD EXAMIANS APP