Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Dump truck Bulldozer Clam shell Scraper Dump truck Bulldozer Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders The several alternatives of the project that have been considered The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The contract documents for inviting tenders ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Clam shell Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (i) and (ii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (iii) are correct (i) and (ii) are correct (ii) and (iii) are correct Only (i) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Dragline Shovel Hoe None of these Dragline Shovel Hoe None of these ANSWER DOWNLOAD EXAMIANS APP