Construction Planning and Management
Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is

1, 2, 3, 4, 5
1, 3, 4, 2, 5
1, 3, 2, 4, 5
1, 2, 4, 3, 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

less than latest event time of preceding node
less than or equal to latest event time of preceding node
equal to latest event time of preceding node
greater than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP