Construction Planning and Management
The technique for establishing and maintaining priorities among the various jobs of a project, is known

Event flow scheduling technique
Slotting technique for scheduling
Short interval scheduling
Critical ratio scheduling

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of both activities A and B are same
expected time of activity B is greater than the expected time of activity A
None of these
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP