Construction Planning and Management The main principle of an organization, is Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels Unity of command All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Total float Interfering float Free float Duration Total float Interfering float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects All listed here Minor projects Any project Major projects All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Most likely time Optimistic time Expected time Pessimistic time Most likely time Optimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP