Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command Delegation of authority All listed here Effective control at all levels Unity of command Delegation of authority All listed here Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg Increase by 200 kg Reduce by 200 kg Increase by 250 kg Reduce by 250 kg ANSWER DOWNLOAD EXAMIANS APP