Construction Planning and Management Free float for any activity is defined as the difference between its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Initiating the procurement action of resources Preparation of specifications Preparation of estimates All listed here Initiating the procurement action of resources Preparation of specifications Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 4350 kg 5515 kg 2975 kg 3425 kg 4350 kg 5515 kg 2975 kg 3425 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP