Construction Planning and Management Free float for any activity is defined as the difference between its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and earliest start time for its successor activity its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 24 19 None of these 14 24 19 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Moist loam Sand and gravel Good common earth Wet sticky clay Moist loam Sand and gravel Good common earth Wet sticky clay ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects should invest in project A should invest in neither of the two projects should invest in project B could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications Raised to meet maintenance costs The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP