Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its latest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these Preceding activities The particular activity involved Succeeding activities None of these Preceding activities The particular activity involved Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 4, 3, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same None of these expected time of activity A is greater than the expected time of activity B expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves All listed here If symmetrical, are called normal curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves All listed here If symmetrical, are called normal curves ANSWER DOWNLOAD EXAMIANS APP