Construction Planning and Management
Free float for any activity is defined as the difference between

its latest finish time and earliest start time for its successor activity
its earliest finish time and latest start time for its successor activity
its latest start time and earliest start time
its earliest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
None of these

ANSWER DOWNLOAD EXAMIANS APP