Construction Planning and Management
Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float

2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

Raised to meet maintenance costs
The fund for rebuilding a structure when its economic life is over
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications