Construction Planning and Management

Construction Planning and Management
Which of the following does not represent an activity?

Site located
The office area is being cleaned
Foundation is being dug
The invitations are being sent

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

Rs. 50000
Rs. 31050
Rs. 34500
Rs. 37950

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

1, 2 and 4 are correct
1, 2 and 3 are correct
2, 3 and 4 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

Rs. 6,50,000
Rs. 4,75,000
Rs. 8,50,000
Rs. 5,75,000

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For a given size of bucket, the ideal output of a dragline will be least in

Sand and gravel
Moist loam
Good common earth
Wet sticky clay

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is

1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 3, 4, 2, 5
1, 2, 3, 4, 5

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑