Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

None of these
expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

Both A and R is true and R is the correct explanation of A
A is false but R is true
A is true but R is false
Both A and R is true but R is not the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Establish priorities
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities, which can be delayed without affecting the total float of succeeding activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iii) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
(i) and (iv) are correct

ANSWER DOWNLOAD EXAMIANS APP