Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
None of these

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The total sum to be paid to the municipal authorities by the tenants
The fund for rebuilding a structure when its economic life is over
A part of the money kept in reserve for providing additional structures and structural modifications
Raised to meet maintenance costs

ANSWER DOWNLOAD EXAMIANS APP