Construction Planning and Management Earliest finish of an activity is always Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Greater than or equal to earliest event time of the following node Less than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Dummy Constraint Free float Event Dummy Constraint Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity Cheapest noncritical activity Costliest noncritical activity Costliest critical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established A project is divided into various activities All listed here Net work is drawn by connecting the activities and the events Required time for each activity is established ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP