Construction Planning and Management
Earliest finish of an activity is always

Greater than earliest event time of the following node
Less than earliest event time of the following node
Less than or equal to earliest event time of the following node
Greater than or equal to earliest event time of the following node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Weighing accurately, the quantity of each material for a job before mixing
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Controlling the quantity of each material into each batch
Controlling the total quantity at each batch

ANSWER DOWNLOAD EXAMIANS APP