Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part All listed here Each individual maintains functional efficiency Strict adherence to specifications Separation of planning and design part ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer Assistant Engineer Superintending Engineer Chief Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Increase of project completion time Decrease of project completion time All of these Change of critical path Increase of project completion time Decrease of project completion time All of these Change of critical path ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 4 days 10 days 6 days 16 days 4 days 10 days 6 days ANSWER DOWNLOAD EXAMIANS APP