Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Project duration time Both resources and project duration time Resources None of these Project duration time Both resources and project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Preceding activities None of these The particular activity involved Succeeding activities Preceding activities None of these The particular activity involved Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A firm All listed here A person An agency A firm All listed here A person ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 16 days 4 days 6 days 10 days 16 days 4 days 6 days ANSWER DOWNLOAD EXAMIANS APP