Construction Planning and Management The constraints in case of resource smoothening operation would be Resources Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 Rs. 1740 Rs. 6960 Rs. 5220 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 85 and 75 80 and 90 75 and 83 90 and 80 85 and 75 80 and 90 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069? Rs. 50000 Rs. 31050 Rs. 37950 Rs. 34500 Rs. 50000 Rs. 31050 Rs. 37950 Rs. 34500 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these The particular activity involved Preceding activities Succeeding activities None of these The particular activity involved Preceding activities Succeeding activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved ANSWER DOWNLOAD EXAMIANS APP