Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Each individual maintains functional efficiency Separation of planning and design part Strict adherence to specifications All listed here Each individual maintains functional efficiency Separation of planning and design part Strict adherence to specifications All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 2-3 is 7 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path On all the activities Only on activities lying on the original critical path and having flatter cost slopes On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 10 days 6 days 4 days 16 days 10 days 6 days 4 days 16 days ANSWER DOWNLOAD EXAMIANS APP