Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time Project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 27 minutes 20.143 minutes 15 minutes 21 minutes 27 minutes 20.143 minutes 15 minutes 21 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 24 None of these 19 14 24 None of these 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP