Construction Planning and Management The basic action involved in sheep foot rolling is Vibration Kneading Tamping Pressing Vibration Kneading Tamping Pressing ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Dummy Event Free float Constraint Dummy Event Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iii) are correct (i) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 3.5 and 5/6 3.5 and 25/36 4 and 5/6 5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An architect An owner All listed here An engineer An architect An owner All listed here ANSWER DOWNLOAD EXAMIANS APP