Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Kneading Vibration Tamping Pressing Kneading Vibration Tamping ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve Beta distribution curve None of these Normal distribution curve Poisson's distribution curve Beta distribution curve None of these Normal distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node less than latest event time of preceding node greater than or equal to latest event time of preceding node equal to latest event time of preceding node less than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 10 days 15 days 8 days 9 days 10 days 15 days 8 days ANSWER DOWNLOAD EXAMIANS APP