Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and free float None of these Total float and independent float Free float and independent float Total float and free float None of these Total float and independent float Free float and independent float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 21 minutes 27 minutes 15 minutes 20.143 minutes 21 minutes 27 minutes 15 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 90 and 80 80 and 90 85 and 75 75 and 83 90 and 80 80 and 90 85 and 75 75 and 83 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Float Constraint Event Duration Float Constraint Event Duration ANSWER DOWNLOAD EXAMIANS APP