Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Project duration time None of these Resources Both resources and project duration time Project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Moist loam Wet sticky clay Well blasted rock Good common earth Moist loam Wet sticky clay Well blasted rock Good common earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 6,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 8,50,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 4,75,000 Rs. 8,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 10 days 9 days 8 days 15 days 10 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Normal time Crash time Slow time Standard time Normal time Crash time Slow time Standard time ANSWER DOWNLOAD EXAMIANS APP