Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 50% at the site and 50% under procurement 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site 50% at the site and 50% under procurement 33% at the site and 67% under procurement 67% at the site and 33% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Line and staff organization Functional organization Line organization Effective organization Line and staff organization Functional organization Line organization Effective organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Concrete cured Fixing of door Selecting sites Plastering of walls Concrete cured Fixing of door Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Duration Constraint Float Event Duration Constraint Float Event ANSWER DOWNLOAD EXAMIANS APP