Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Clam shell Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Minor projects All listed here Major projects Any project Minor projects All listed here Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Frequency distribution curves If symmetrical, are called normal curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves All listed here If symmetrical, are called normal curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves All listed here ANSWER DOWNLOAD EXAMIANS APP