Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 20 kg/tonne 2 kg/tonne 9 kg/tonne 6 kg/tonne 20 kg/tonne 2 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 24 19 14 None of these 24 19 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in costs for the removal of defects Reduction in wastage of inspection costs Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Total float Free float Interfering float Independent float Total float Free float Interfering float Independent float ANSWER DOWNLOAD EXAMIANS APP