Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time None of these Project duration time Resources Both resources and project duration time None of these Project duration time Resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 14 days 19 days 13 days 9 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 3 and 4 are correct 1, 2 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Normal time Crash time Between normal time and crash time Optimistic time Normal time Crash time Between normal time and crash time Optimistic time ANSWER DOWNLOAD EXAMIANS APP