Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float Maximum float Zero float None of these Minimum float Maximum float Zero float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Assistant Engineer Executive Engineer Engineer Junior Engineer Assistant Engineer Executive Engineer Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 1740 Rs. 5220 Rs. 6960 Rs. 3480 Rs. 1740 Rs. 5220 Rs. 6960 Rs. 3480 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time with which direct cost does not reduce with the increase in time is known as Standard time Crash time Optimistic time Normal time Standard time Crash time Optimistic time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Maximum Minimum Zero Infinite Maximum Minimum Zero ANSWER DOWNLOAD EXAMIANS APP