Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Survey of the site Preparation of estimate Initiation of proposal Preparation of tender Survey of the site Preparation of estimate Initiation of proposal ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP