Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is None of these Dragline Hoe Shovel None of these Dragline Hoe Shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 6 days 16 days 10 days 4 days 6 days 16 days 10 days 4 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site 33% at the site and 67% under procurement ANSWER DOWNLOAD EXAMIANS APP