Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Resources None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an event? Fixing of door Concrete cured Selecting sites Plastering of walls Fixing of door Concrete cured Selecting sites Plastering of walls ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 10000 kg 22500 kg 12500 kg 5000 kg 10000 kg 22500 kg 12500 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP