• HOME
  • QUIZ
  • CONTACT US
EXAMIANS
  • COMPUTER
  • CURRENT AFFAIRS
  • ENGINEERING
    • Chemical Engineering
    • Civil Engineering
    • Computer Engineering
    • Electrical Engineering
    • Mechanical Engineering
  • ENGLISH GRAMMAR
  • GK
  • GUJARATI MCQ

Construction Planning and Management

Construction Planning and Management
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

(a + 4m + b)/6
(a + m + b)/6
(a + 5m + b)/6
(a + 2m + b)/6

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

None of these
24
14
19

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

Rs. 4,75,000
Rs. 5,75,000
Rs. 8,50,000
Rs. 6,50,000

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

Rs. 50000
Rs. 34500
Rs. 31050
Rs. 37950

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of projectPERT is preferred for planning because of

1, 3 and 4
3, 4 and 5
1, 2 and 4
1, 2 and 5

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In resources levelling

Total duration of project is reduced
Cost of project is controlled
Uniform demand of resources is achieved
Total duration of project is increased

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑