Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 9 days 19 days 13 days 14 days 9 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Earliest finish of an activity is always Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node Greater than earliest event time of the following node Less than or equal to earliest event time of the following node Greater than or equal to earliest event time of the following node Less than earliest event time of the following node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Preliminary project report for a road project must contain The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design The soil survey, traffic survey, concept design and approximate cost The several alternatives of the project that have been considered The contract documents for inviting tenders The detailed estimated cost based on detailed design ANSWER DOWNLOAD EXAMIANS APP