Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Chief Engineer Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer Assistant Engineer Executive Engineer Superintending Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B should invest in project A could invest in either of the two projects should invest in neither of the two projects should invest in project B ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne 20 kg/tonne 30 kg/tonne 40 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP