Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources All listed here Preparation of estimates Preparation of specifications Initiating the procurement action of resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP