Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties Interdependencies of activities All of these Project progress Uncertainties Interdependencies of activities All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Names of the casual labour Issue of store equipments Instructions by the executive engineers Construction measurements Names of the casual labour Issue of store equipments Instructions by the executive engineers Construction measurements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 15 minutes 21 minutes 27 minutes 20.143 minutes 15 minutes 21 minutes 27 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP