Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Industrial construction Light construction Private construction Heavy construction Industrial construction Light construction Private construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Smooth-wheeled rollers Vibratory rollers Sheep foot rollers Tampers Smooth-wheeled rollers Vibratory rollers Sheep foot rollers Tampers ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 50% at the site and 50% under procurement 33% at the site and 67% under procurement 100% at the site 67% at the site and 33% under procurement 50% at the site and 50% under procurement 33% at the site and 67% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between None of these Total float and independent float Free float and independent float Total float and free float None of these Total float and independent float Free float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP