Construction Planning and Management

Construction Planning and Management
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

(a + m + b)/6
(a + 5m + b)/6
(a + 4m + b)/6
(a + 2m + b)/6

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In resources levelling

Total duration of project is increased
Uniform demand of resources is achieved
Cost of project is controlled
Total duration of project is reduced

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The normal time required for the completion of project in the above problem is

19 days
14 days
13 days
9 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is

1, 3, 4, 2
1, 3, 2, 4
3, 1, 2, 4
3, 1, 4, 2

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

900 kg
300 kg
1000 kg
30 kg

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

3
4
1
2

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Construction Planning and Management

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑