Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 1, 2 and 5 1, 2 and 4 1, 3 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above More than X Less than X Equal to X Any of the above More than X Less than X Equal to X ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting All listed here Number of operations Output of machinery Output of labour All listed here Number of operations Output of machinery Output of labour ANSWER DOWNLOAD EXAMIANS APP