Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in costs for the removal of defects
Measurement of risks to eliminate failures
Applying the theory' of probability to sample testing or inspection
Reduction in wastage of inspection costs

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For all activities required to start the work at site on finalization of the contract document
For the payment of advances to labour and other staff

ANSWER DOWNLOAD EXAMIANS APP