Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and increasing indirect cost
Decreasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Normal durations for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

ANSWER DOWNLOAD EXAMIANS APP