Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced Total duration of project is increased Uniform demand of resources is achieved Cost of project is controlled Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 14 days 13 days 9 days 19 days 14 days 13 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 1, 3, 4, 2 1, 3, 2, 4 3, 1, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 900 kg 300 kg 1000 kg 30 kg 900 kg 300 kg 1000 kg 30 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 3 4 1 2 3 4 1 2 ANSWER DOWNLOAD EXAMIANS APP