Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct Both A and R is incorrect R is correct but A is not correct A is correct but R is not correct Both A and R is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Between normal time and crash time Normal time Crash time Optimistic time Between normal time and crash time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over The total sum to be paid to the municipal authorities by the tenants Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 250 kg Reduce by 250 kg Reduce by 200 kg Increase by 200 kg Increase by 250 kg Reduce by 250 kg Reduce by 200 kg Increase by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Batching refers to Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch Weighing accurately, the quantity of each material for a job before mixing Controlling the quantity of each material into each batch Controlling the total quantity at each batch Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch ANSWER DOWNLOAD EXAMIANS APP