Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these Zero float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Extraordinary delay in communications Top level executions over work Rigid structure All listed here Extraordinary delay in communications Top level executions over work Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1910 1940 1930 1920 1910 1940 1930 1920 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection Reduction in costs for the removal of defects Reduction in wastage of inspection costs Measurement of risks to eliminate failures Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP