Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these Adjusts automatically changes in activity progress Is a dynamic system Determines the status of each activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey All listed here Availability of construction materials Availability of labour Site survey All listed here Availability of construction materials Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Concrete Loose sand Earth Ice Concrete Loose sand Earth Ice ANSWER DOWNLOAD EXAMIANS APP