Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An activity An event Both event and activity None of these An activity An event Both event and activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Total float Interfering float Free float Duration Total float Interfering float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency A firm All listed here A person An agency A firm All listed here A person ANSWER DOWNLOAD EXAMIANS APP