Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 1, 2 and 4 1, 2 and 5 1, 3 and 4 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float None of these Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Preceding activities The particular activity involved None of these Succeeding activities Preceding activities The particular activity involved None of these Succeeding activities ANSWER DOWNLOAD EXAMIANS APP