Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Free float and independent float None of these Total float and independent float Total float and free float Free float and independent float None of these Total float and independent float Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? All listed here Excavation for foundation Setting of question paper Curing of concrete All listed here Excavation for foundation Setting of question paper Curing of concrete ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP