Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Resources None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 5000 kg 22500 kg 10000 kg 12500 kg 5000 kg 22500 kg 10000 kg 12500 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Number of operations All listed here Output of labour Output of machinery Number of operations All listed here Output of labour Output of machinery ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time ANSWER DOWNLOAD EXAMIANS APP