Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 13 days 19 days 14 days 9 days 13 days 19 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as None of these Heavy construction Industrial construction Light construction None of these Heavy construction Industrial construction Light construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Interfering float Free float Total float Duration Interfering float Free float Total float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour All listed here Site survey Availability of construction materials Availability of labour All listed here Site survey Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP