Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects should invest in project B should invest in project A should invest in neither of the two projects could invest in either of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 Rs. 6,400 Rs. 5,000 Rs. 7,600 Rs. 8,800 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Foundation is being dug The invitations are being sent The office area is being cleaned Site located Foundation is being dug The invitations are being sent The office area is being cleaned Site located ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP