Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities All of these Project progress Uncertainties Interdependencies of activities All of these Project progress Uncertainties ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 2 kg/tonne 20 kg/tonne 6 kg/tonne 9 kg/tonne 2 kg/tonne 20 kg/tonne 6 kg/tonne 9 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Crash time Optimistic time Between normal time and crash time Normal time Crash time Optimistic time Between normal time and crash time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.841 1 0.5 0.999 0.841 1 0.5 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP