Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most popular type of organization used for Civil Engineering Constructions, is Line and staff organization Functional organization Line organization Effective organization Line and staff organization Functional organization Line organization Effective organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Earth Concrete Ice Loose sand Earth Concrete Ice Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 14 days 19 days 9 days 13 days 14 days 19 days 9 days ANSWER DOWNLOAD EXAMIANS APP