Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Milestone chart Bar chart method Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Milestone chart Bar chart method ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 35 15 20 25 35 15 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in All of these Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time ANSWER DOWNLOAD EXAMIANS APP