Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Heavy construction Light construction Industrial construction Electrical construction Heavy construction Light construction Industrial construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An event Both event and activity An activity None of these An event Both event and activity An activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A expected time of both activities A and B are same expected time of activity A is greater than the expected time of activity B None of these expected time of activity B is greater than the expected time of activity A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Expected time Pessimistic time Optimistic time Most likely time Expected time Pessimistic time Optimistic time Most likely time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Industrial construction Heavy construction None of these Light construction Industrial construction Heavy construction None of these Light construction ANSWER DOWNLOAD EXAMIANS APP