Construction Planning and Management
Earliest finish of an activity is always

Less than or equal to earliest event time of the following node
Greater than or equal to earliest event time of the following node
Greater than earliest event time of the following node
Less than earliest event time of the following node

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
Raised to meet maintenance costs
The fund for rebuilding a structure when its economic life is over

ANSWER DOWNLOAD EXAMIANS APP