Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 4,75,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 6,50,000 Rs. 4,75,000 Rs. 8,50,000 Rs. 5,75,000 Rs. 6,50,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be More than 50 % 0.5 Less than 50 % 1 More than 50 % 0.5 Less than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? All of these Uncertainties Project progress Interdependencies of activities All of these Uncertainties Project progress Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here ANSWER DOWNLOAD EXAMIANS APP