Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 (a + 4m + b)/6 (a + 5m + b)/6 (a + m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as None of these Industrial construction Light construction Heavy construction None of these Industrial construction Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Slotting technique for scheduling Critical ratio scheduling Event flow scheduling technique Short interval scheduling Slotting technique for scheduling Critical ratio scheduling Event flow scheduling technique Short interval scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 19 14 None of these 24 19 14 None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors? Ice Concrete Loose sand Earth Ice Concrete Loose sand Earth ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP