Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 1 0.999 0.841 0.5 1 0.999 0.841 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 1-2 is 4 2-3 is 7 All listed here 3-4 is 8 1-2 is 4 2-3 is 7 All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Constraint Free float Dummy Event Constraint Free float Dummy ANSWER DOWNLOAD EXAMIANS APP