Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Drag line Clam shell Dipper shovel Hoe Drag line Clam shell Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 3, 4 and 5 1, 2 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct Both A and R is incorrect Both A and R is correct A is correct but R is not correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 3-4 is 8 All listed here 2-3 is 7 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Preparation of tender Initiation of proposal Preparation of estimate Survey of the site Preparation of tender Initiation of proposal Preparation of estimate Survey of the site ANSWER DOWNLOAD EXAMIANS APP