Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Drag line Clam shell Dipper shovel Hoe Drag line Clam shell Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An engineer An owner All listed here An architect An engineer An owner All listed here An architect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 4 3 1 2 4 3 1 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 15 days 10 days 9 days 8 days 15 days 10 days 9 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 5,000 Rs. 6,400 Rs. 8,800 Rs. 7,600 Rs. 5,000 Rs. 6,400 Rs. 8,800 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP