Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 4 2 3 1 4 2 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Clam shell Dipper shovel Drag line Hoe Clam shell Dipper shovel Drag line Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 19 days 13 days 9 days 14 days 19 days 13 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP