Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time which results in the least possible construction cost of an activity, is known as Crash time Standard time Slow time Normal time Crash time Standard time Slow time Normal time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only Preceding activities Succeeding activities None of these The particular activity involved Preceding activities Succeeding activities None of these The particular activity involved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP