Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity Is a dynamic system None of these Adjusts automatically changes in activity progress Determines the status of each activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is None of these 24 14 19 None of these 24 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Resource smoothening Critical path scheduling Updating Resource levelling Resource smoothening Critical path scheduling Updating Resource levelling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1920 1910 1930 1940 1920 1910 1930 ANSWER DOWNLOAD EXAMIANS APP