Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum time Maximum time Minimum cost Maximum cost Minimum time Maximum time Minimum cost Maximum cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:Drive wheels: 25000 kgScraper wheels: 10000 kgIf the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is 22500 kg 10000 kg 12500 kg 5000 kg 22500 kg 10000 kg 12500 kg 5000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 9 days 10 days 8 days 15 days 9 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP