Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Drag line Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 Rs. 10,50,000 Rs. 11,56,250 Rs. 8,75,000 Rs. 8,43,750 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer Executive Engineer Superintending Engineer Assistant Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 3, 1, 2, 4 1, 3, 2, 4 1, 3, 4, 2 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 9 days 15 days 10 days 8 days 9 days 15 days 10 days 8 days ANSWER DOWNLOAD EXAMIANS APP