Construction Planning and Management
Preliminary project report for a road project must contain

The soil survey, traffic survey, concept design and approximate cost
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The contract documents for inviting tenders

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All listed here

ANSWER DOWNLOAD EXAMIANS APP