Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Power stations are generally treated as Light construction Heavy construction Electrical construction Industrial construction Light construction Heavy construction Electrical construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Optimistic time Pessimistic time All listed here Most likely time Optimistic time Pessimistic time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 40 kg/tonne 20 kg/tonne 30 kg/tonne 50 kg/tonne 40 kg/tonne 20 kg/tonne 30 kg/tonne 50 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart ANSWER DOWNLOAD EXAMIANS APP