Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Bar chart method Milestone chart Programme Evaluation and Review Technique (PERT) Critical path method (CPM) Bar chart method Milestone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Highest cost slope Longest duration Least cost slope Shortest duration Highest cost slope Longest duration Least cost slope Shortest duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Interfering float is the difference between Total float and independent float Free float and independent float None of these Total float and free float Total float and independent float Free float and independent float None of these Total float and free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects All listed here Minor projects Any project Major projects All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP