Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Clam shell Drag line Dipper shovel Hoe Clam shell Drag line Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Heavy construction None of these Light construction Industrial construction Heavy construction None of these Light construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Pessimistic time Optimistic time Expected time Most likely time Pessimistic time Optimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Event Free float Constraint Dummy Event Free float Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement 50% at the site and 50% under procurement 67% at the site and 33% under procurement 100% at the site 33% at the site and 67% under procurement ANSWER DOWNLOAD EXAMIANS APP