Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Hoe Drag line Dipper shovel Clam shell Hoe Drag line Dipper shovel Clam shell ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT technique of network analysis is mainly useful for Deterministic activities Small projects Research and development projects Large and complex projects Deterministic activities Small projects Research and development projects Large and complex projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Top level executions over work Extraordinary delay in communications Rigid structure All listed here Top level executions over work Extraordinary delay in communications Rigid structure All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased Cost of project is controlled Uniform demand of resources is achieved Total duration of project is reduced Total duration of project is increased ANSWER DOWNLOAD EXAMIANS APP