Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Drag line Clam shell Dipper shovel Hoe Drag line Clam shell Dipper shovel Hoe ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 2000 cum 1000 cum 500 cum 1500 cum 2000 cum 1000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Names of the casual labour Issue of store equipments Construction measurements Instructions by the executive engineers Names of the casual labour Issue of store equipments Construction measurements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Rate of inflation ANSWER DOWNLOAD EXAMIANS APP