Construction Planning and Management Slack time refers to An activity Both event and activity None of these An event An activity Both event and activity None of these An event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Interfering float Total float Independent float Free float Interfering float Total float Independent float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Initiation of proposal Preparation of tender Survey of the site Preparation of estimate Initiation of proposal Preparation of tender Survey of the site Preparation of estimate ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float is mainly used to Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities Identify the activities which can be delayed without affecting the total float of preceding activity Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Identify the activities, which can be delayed without affecting the total float of succeeding activity Establish priorities ANSWER DOWNLOAD EXAMIANS APP