Construction Planning and Management Slack time refers to Both event and activity An event An activity None of these Both event and activity An event An activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% 2.3% and 84.1% 97.7 % and 15.9% 15.9% and 97.7% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity Cheapest noncritical activity Cheapest critical activity Costliest noncritical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 14 days 13 days 9 days 19 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Optimistic time All listed here Most likely time Pessimistic time Optimistic time All listed here Most likely time ANSWER DOWNLOAD EXAMIANS APP