Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Dummy Event Free float Constraint Dummy Event Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress Uncertainties All of these Interdependencies of activities Project progress Uncertainties All of these Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The independent float affects only None of these Preceding activities Succeeding activities The particular activity involved None of these Preceding activities Succeeding activities The particular activity involved ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Rigid structure Top level executions over work Extraordinary delay in communications All listed here Rigid structure Top level executions over work Extraordinary delay in communications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Pessimistic time Expected time Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time ANSWER DOWNLOAD EXAMIANS APP