Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Event Dummy Constraint Free float Event Dummy Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 4 1 3 2 4 1 3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled Total duration of project is increased Uniform demand of resources is achieved Total duration of project is reduced Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The most suitable type of equipment for compaction of cohesive soils is Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers Vibratory rollers Smooth-wheeled rollers Sheep foot rollers Tampers ANSWER DOWNLOAD EXAMIANS APP