Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Free float Dummy Constraint Event Free float Dummy Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means An architect All listed here An engineer An owner An architect All listed here An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 21 minutes 27 minutes 20.143 minutes 15 minutes 21 minutes 27 minutes 20.143 minutes 15 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Site order book is used for recording Instructions by the executive engineers Issue of store equipments Names of the casual labour Construction measurements Instructions by the executive engineers Issue of store equipments Names of the casual labour Construction measurements ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Positive Same Zero Negative Positive Same Zero ANSWER DOWNLOAD EXAMIANS APP