Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Constraint Event Dummy Free float Constraint Event Dummy ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Crash time Normal time Between normal time and crash time Optimistic time Crash time Normal time Between normal time and crash time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Critical path scheduling Resource levelling Updating Resource smoothening Critical path scheduling Resource levelling Updating Resource smoothening ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Both resources and project duration time Resources Project duration time None of these Both resources and project duration time Resources Project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Change in output due to change in input Comparison of profit and loss Comparison of assets and liabilities Economics of cost and benefits of the project Change in output due to change in input Comparison of profit and loss Comparison of assets and liabilities Economics of cost and benefits of the project ANSWER DOWNLOAD EXAMIANS APP