Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Event Free float Dummy Constraint Event Free float Dummy Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Foundation is being dug The invitations are being sent Site located The office area is being cleaned Foundation is being dug The invitations are being sent Site located The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively 75 and 83 80 and 90 90 and 80 85 and 75 75 and 83 80 and 90 90 and 80 85 and 75 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Horizontal lines Crosses Dots Vertical lines Horizontal lines Crosses Dots Vertical lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Free float Total float Interfering float Independent float Free float Total float Interfering float Independent float ANSWER DOWNLOAD EXAMIANS APP