Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Dummy Constraint Free float Event Dummy Constraint Free float Event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 3, 1, 4, 2 1, 3, 2, 4 1, 3, 4, 2 3, 1, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Junior Engineer Assistant Engineer Engineer Executive Engineer Junior Engineer Assistant Engineer Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties Project progress All of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP