A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

21 minutes
20.143 minutes
15 minutes
27 minutes

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Controlling the total quantity at each batch
Controlling the quantity of each material into each batch
Weighing accurately, the quantity of each material for a job before mixing
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch