Construction Planning and Management The object of technical planning, is All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 None of these 14 19 24 None of these 14 19 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Hoe Shovel Dragline None of these Hoe Shovel Dragline None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input Economics of cost and benefits of the project Comparison of assets and liabilities Comparison of profit and loss Change in output due to change in input Economics of cost and benefits of the project ANSWER DOWNLOAD EXAMIANS APP