Construction Planning and Management
The object of technical planning, is

Initiating the procurement action of resources
Preparation of specifications
Preparation of estimates
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

None of these
expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same
expected time of activity B is greater than the expected time of activity A

ANSWER DOWNLOAD EXAMIANS APP