Construction Planning and Management
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is

1, 3, 2, 4, 5
1, 3, 4, 2, 5
1, 2, 4, 3, 5
1, 2, 3, 4, 5