Construction Planning and Management The first method invented for planning projects, was Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method Critical path method (CPM) Programme Evaluation and Review Technique (PERT) Milestone chart Bar chart method ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 67% at the site and 33% under procurement 50% at the site and 50% under procurement 33% at the site and 67% under procurement 100% at the site 67% at the site and 33% under procurement 50% at the site and 50% under procurement 33% at the site and 67% under procurement 100% at the site ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff On commencement of work at site for payment of loan taken by him For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials For the payment of advances to labour and other staff ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 20 kg/tonne 9 kg/tonne 2 kg/tonne 6 kg/tonne 20 kg/tonne 9 kg/tonne 2 kg/tonne 6 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Negative Positive Zero Same Negative Positive Zero Same ANSWER DOWNLOAD EXAMIANS APP