Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Clam shell Bulldozer Dump truck Scraper Clam shell Bulldozer Dump truck ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Pessimistic time Expected time Optimistic time Most likely time Pessimistic time Expected time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Availability of labour All listed here Availability of construction materials Site survey Availability of labour All listed here Availability of construction materials Site survey ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Interfering float Free float Duration Total float Interfering float Free float Duration ANSWER DOWNLOAD EXAMIANS APP