Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Clam shell Dump truck Bulldozer Scraper Clam shell Dump truck Bulldozer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 20 kg/tonne 2 kg/tonne 9 kg/tonne 6 kg/tonne 20 kg/tonne 2 kg/tonne 9 kg/tonne 6 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 10 days 9 days 15 days 8 days 10 days 9 days 15 days 8 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A CPM family includes CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here CPA (Critical Path Analysis) MCE (Minimum Cost Expenditure) CPP (Critical Path Plotted) All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D LS = LF - D EF = ES + D All listed here LF = LS + D LS = LF - D EF = ES + D All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Longest duration Highest cost slope Shortest duration Least cost slope Longest duration Highest cost slope Shortest duration Least cost slope ANSWER DOWNLOAD EXAMIANS APP