Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project All listed here Major projects Minor projects Any project All listed here Major projects Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Assistant Engineer Engineer Junior Engineer Executive Engineer Assistant Engineer Engineer Junior Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Maximum Minimum Infinite Zero Maximum Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 500 cum 1000 cum 2000 cum 1500 cum 500 cum 1000 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 Rs. 11,56,250 Rs. 8,43,750 Rs. 10,50,000 Rs. 8,75,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP