Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Minor projects Major projects Any project All listed here Minor projects Major projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 2 1 3 4 2 1 3 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is All listed here Unity of command Delegation of authority Effective control at all levels All listed here Unity of command Delegation of authority Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Drag line Clam shell Hoe Dipper shovel Drag line Clam shell Hoe Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 1000 kg 900 kg 30 kg 300 kg 1000 kg 900 kg 30 kg 300 kg ANSWER DOWNLOAD EXAMIANS APP