Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Any project Major projects Minor projects All listed here Any project Major projects Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Various activities of a project, are shown on bar charts by Dots Crosses Vertical lines Horizontal lines Dots Crosses Vertical lines Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Increase of project completion time All of these Change of critical path Decrease of project completion time Increase of project completion time All of these Change of critical path Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is 5515 kg 2975 kg 4350 kg 3425 kg 5515 kg 2975 kg 4350 kg 3425 kg ANSWER DOWNLOAD EXAMIANS APP