Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects Any project All listed here Major projects Minor projects Any project All listed here Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 20 15 35 25 20 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 27 minutes 21 minutes 15 minutes 20.143 minutes 27 minutes 21 minutes 15 minutes 20.143 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1000 cum 1500 cum 500 cum 2000 cum 1000 cum 1500 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 4tm+ tp/4 to + 3tm+ tp/3 to + 4tm+ tp/6 to + 4tm+ tp/5 to + 4tm+ tp/4 ANSWER DOWNLOAD EXAMIANS APP