Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects All listed here Minor projects Any project Major projects All listed here Minor projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document For the purchase of construction materials On commencement of work at site for payment of loan taken by him ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Construction team means All listed here An architect An engineer An owner All listed here An architect An engineer An owner ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP