Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects Any project All listed here Major projects Minor projects Any project All listed here Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 8,43,750 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 Rs. 8,43,750 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to 6 kg/tonne 9 kg/tonne 2 kg/tonne 20 kg/tonne 6 kg/tonne 9 kg/tonne 2 kg/tonne 20 kg/tonne ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mobilization advance up to 10% of the cost of work is given to a contractor For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials For the payment of advances to labour and other staff For all activities required to start the work at site on finalization of the contract document On commencement of work at site for payment of loan taken by him For the purchase of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer Assistant Engineer Executive Engineer Superintending Engineer Chief Engineer ANSWER DOWNLOAD EXAMIANS APP