Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Minor projects Any project Major projects All listed here Minor projects Any project Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Required time for each activity is established All listed here A project is divided into various activities Net work is drawn by connecting the activities and the events Required time for each activity is established All listed here A project is divided into various activities Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first method invented for planning projects, was Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) Bar chart method Programme Evaluation and Review Technique (PERT) Milestone chart Critical path method (CPM) ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Optimistic time Most likely time All listed here Pessimistic time Optimistic time Most likely time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% 2.3% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP