Construction Planning and Management
Whenever an activity has zero total float, then

Free float of the activity must be zero but independent float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Independent float must be zero but free float need not be zero

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document

ANSWER DOWNLOAD EXAMIANS APP