Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Any project Major projects Minor projects All listed here Any project Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Decreasing the direct cost and increasing indirect cost Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and indirect cost both ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Resources None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 3 are correct 1, 2 and 4 are correct 1 and 4 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time corresponding to minimum total project cost is Optimistic time Between normal time and crash time Normal time Crash time Optimistic time Between normal time and crash time Normal time Crash time ANSWER DOWNLOAD EXAMIANS APP