Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Major projects Any project Minor projects All listed here Major projects Any project Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 3, 1, 4, 2 1, 3, 2, 4 3, 1, 2, 4 1, 3, 4, 2 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iv) are correct (ii) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (iv) are correct (ii) and (iv) are correct (i) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The difference between the time avail-to do a job and the time required to do the job, is known as Event Constraint Duration Float Event Constraint Duration Float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The probability of completion of any activity within its expected time is 0.5 0.841 1 0.999 0.5 0.841 1 0.999 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Expected time Optimistic time Pessimistic time Most likely time Expected time Optimistic time Pessimistic time ANSWER DOWNLOAD EXAMIANS APP