Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Major projects Minor projects Any project All listed here Major projects Minor projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Modified Mile stone chart Bar chart Gantt chart All listed here Modified Mile stone chart Bar chart Gantt chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg Reduce by 200 kg Increase by 200 kg Reduce by 250 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress All of these Interdependencies of activities Uncertainties Project progress All of these Interdependencies of activities Uncertainties ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 30 kg 900 kg 300 kg 1000 kg 30 kg 900 kg 300 kg 1000 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct 1 and 2 are correct 2 and 3 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP