Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects All listed here Minor projects Any project Major projects All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path Is always shortest May be longest May be shortest Is always longest Is always shortest May be longest May be shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be 20 kg/tonne 40 kg/tonne 50 kg/tonne 30 kg/tonne 20 kg/tonne 40 kg/tonne 50 kg/tonne 30 kg/tonne ANSWER DOWNLOAD EXAMIANS APP