Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects Minor projects Any project All listed here Major projects Minor projects Any project All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as All listed here Gantt chart Modified Mile stone chart Bar chart All listed here Gantt chart Modified Mile stone chart Bar chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials Rate of inflation Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled Total duration of project is reduced Uniform demand of resources is achieved Total duration of project is increased Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP