Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects All listed here Minor projects Any project Major projects All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 27 minutes 15 minutes 21 minutes 20.143 minutes 27 minutes 15 minutes 21 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is a weakness of bar chart? Project progress All of these Uncertainties Interdependencies of activities Project progress All of these Uncertainties Interdependencies of activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following does not represent an activity? Foundation is being dug The invitations are being sent Site located The office area is being cleaned Foundation is being dug The invitations are being sent Site located The office area is being cleaned ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 8 days 10 days 15 days 9 days 8 days 10 days 15 days 9 days ANSWER DOWNLOAD EXAMIANS APP