Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Major projects Any project Minor projects All listed here Major projects Any project Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as Line and staff organization None of these Functional organization Line organization Line and staff organization None of these Functional organization Line organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Duration Interfering float Free float Total float Duration Interfering float Free float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum 500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers All listed here Site survey Availability of labour Availability of construction materials All listed here Site survey Availability of labour Availability of construction materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 Rs. 7,600 Rs. 6,400 Rs. 5,000 Rs. 8,800 ANSWER DOWNLOAD EXAMIANS APP