Construction Planning and Management Works costing less than Rs. 20,000 are treated as Minor projects All listed here Any project Major projects Minor projects All listed here Any project Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Critical path scheduling Resource levelling Resource smoothening Updating Critical path scheduling Resource levelling Resource smoothening ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The basic action involved in sheep foot rolling is Pressing Vibration Tamping Kneading Pressing Vibration Tamping Kneading ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 14 days 19 days 9 days 13 days 14 days 19 days 9 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest start time and earliest finish time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct Only (i) is correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP