Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects All listed here Minor projects Any project Major projects All listed here Minor projects Any project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same None of these expected time of activity B is greater than the expected time of activity A expected time of activity A is greater than the expected time of activity B expected time of both activities A and B are same ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Reduction in wastage of inspection costs Measurement of risks to eliminate failures Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having Shortest duration Longest duration Least cost slope Highest cost slope Shortest duration Longest duration Least cost slope Highest cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is 30 kg 1000 kg 900 kg 300 kg 30 kg 1000 kg 900 kg 300 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity All listed here 2-3 is 7 3-4 is 8 1-2 is 4 All listed here 2-3 is 7 3-4 is 8 1-2 is 4 ANSWER DOWNLOAD EXAMIANS APP