Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Minor projects Major projects All listed here Any project Minor projects Major projects All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path lies along the activities having total float Positive Zero Same Negative Positive Zero Same Negative ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve Normal distribution curve None of these Beta distribution curve Poisson's distribution curve Normal distribution curve None of these Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 3, 1, 4, 2 1, 3, 4, 2 3, 1, 2, 4 1, 3, 2, 4 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% 97.7% and 84.1% 15.9% and 97.7% 2.3% and 84.1% 97.7 % and 15.9% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Rolling resistance of a wheel depends upon(i) Vehicle load(ii) Grade(iii) Ground conditions (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct (ii) and (iii) are correct (i) and (ii) are correct (i) and (iii) are correct Only (i) is correct ANSWER DOWNLOAD EXAMIANS APP