Construction Planning and Management Works costing less than Rs. 20,000 are treated as All listed here Minor projects Any project Major projects All listed here Minor projects Any project Major projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated. 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct 1 and 4 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Interfering float Duration Free float Total float Interfering float Duration Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Crash durations for all activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope On all the activities lying on the critical path Only on activities lying on the original critical path and having flatter cost slopes On all the activities On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 4 2 3 1 4 2 3 ANSWER DOWNLOAD EXAMIANS APP