Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects Any project All listed here Minor projects Major projects Any project All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Heavy construction Industrial construction Light construction None of these Heavy construction Industrial construction Light construction None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 5 and 25/36 4 and 5/6 3.5 and 25/36 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Preparation of specifications Preparation of estimates All listed here Initiating the procurement action of resources Preparation of specifications Preparation of estimates All listed here Initiating the procurement action of resources ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP