Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest finish time
Its latest start time and earliest start time
Its earliest finish time and earliest start time for its successor activity
Its latest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP