Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

Yes, because of heavier overheads and handling cost
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour
Yes, because of the very high order of quality control for the factory made components

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same
None of these

ANSWER DOWNLOAD EXAMIANS APP