Construction Planning and Management
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

1, 2 and 4 are correct
2, 3 and 4 are correct
1 and 4 are correct
1, 2 and 3 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The soil survey, traffic survey, concept design and approximate cost
The several alternatives of the project that have been considered
The contract documents for inviting tenders
The detailed estimated cost based on detailed design

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP