Construction Planning and Management
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

1, 2 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1 and 4 are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of both activities A and B are same
None of these
expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Free float is mainly used to

Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Identify the activities which can be delayed without affecting the total float of preceding activity
Establish priorities

ANSWER DOWNLOAD EXAMIANS APP