Construction Planning and Management
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

2000 cum
1000 cum
500 cum
1500 cum

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth.
(iv) Output can be increased by increasing the size of shovel.

(ii), (iii) and (iv) are correct
(i), (ii) and (iv) are correct
(i) and (iv) are correct
(i), (iii) and (iv) are correct

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Preliminary project report for a road project must contain

The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders

ANSWER DOWNLOAD EXAMIANS APP