Construction Planning and Management Economic saving of time results by crashing Costliest critical activity Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity Costliest critical activity Costliest noncritical activity Cheapest noncritical activity Cheapest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be Rs. 5,000 Rs. 6,400 Rs. 8,800 Rs. 7,600 Rs. 5,000 Rs. 6,400 Rs. 8,800 Rs. 7,600 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management At a work site, statistical quality control of concrete means Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs Reduction in costs for the removal of defects Applying the theory' of probability to sample testing or inspection Measurement of risks to eliminate failures Reduction in wastage of inspection costs Reduction in costs for the removal of defects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 4 and 5/6 5 and 25/36 3.5 and 25/36 3.5 and 5/6 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero Free float and independent float both must be zero Independent float must be zero but free float need not be zero Free float of the activity must be zero but independent float need not be zero Free float and independent float both need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs A part of the money kept in reserve for providing additional structures and structural modifications The total sum to be paid to the municipal authorities by the tenants ANSWER DOWNLOAD EXAMIANS APP