Construction Planning and Management Various activities of a project, are shown on bar charts by Dots Vertical lines Horizontal lines Crosses Dots Vertical lines Horizontal lines Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 8 days 9 days 10 days 15 days 8 days 9 days 10 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Interfering float Total float Duration Free float Interfering float Total float Duration ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established A project is divided into various activities Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The Overall in-charge of an organization at the site responsible for the execution of the works, is Junior Engineer Executive Engineer Engineer Assistant Engineer Junior Engineer Executive Engineer Engineer Assistant Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Any of the above More than X Equal to X Less than X Any of the above More than X Equal to X Less than X ANSWER DOWNLOAD EXAMIANS APP