Construction Planning and Management Various activities of a project, are shown on bar charts by Horizontal lines Vertical lines Dots Crosses Horizontal lines Vertical lines Dots Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Duration Interfering float Total float Free float Duration Interfering float Total float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The process of incorporating changes and rescheduling or replanning is called Updating Critical path scheduling Resource smoothening Resource levelling Updating Critical path scheduling Resource smoothening Resource levelling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Optimistic time Pessimistic time Most likely time All listed here Optimistic time Pessimistic time Most likely time All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is Rs. 10,50,000 Rs. 8,43,750 Rs. 8,75,000 Rs. 11,56,250 Rs. 10,50,000 Rs. 8,43,750 Rs. 8,75,000 Rs. 11,56,250 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is 15 days 10 days 8 days 9 days 15 days 10 days 8 days 9 days ANSWER DOWNLOAD EXAMIANS APP