Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Vertical lines Horizontal lines Dots Crosses Vertical lines Horizontal lines Dots ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Private construction Industrial construction Light construction Heavy construction Private construction Industrial construction Light construction Heavy construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 19 days 9 days 14 days 13 days 19 days 9 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A critical ratio scheduling Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these Is a dynamic system Adjusts automatically changes in activity progress Determines the status of each activity None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In resources levelling Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced Uniform demand of resources is achieved Cost of project is controlled Total duration of project is increased Total duration of project is reduced ANSWER DOWNLOAD EXAMIANS APP