Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Horizontal lines Dots Crosses Vertical lines Horizontal lines Dots Crosses ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 20 25 15 35 20 25 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Effective control at all levels All listed here Delegation of authority Unity of command Effective control at all levels All listed here Delegation of authority Unity of command ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Pessimistic time Most likely time All listed here Optimistic time Pessimistic time Most likely time All listed here Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 2000 cum 500 cum 1000 cum 1500 cum 2000 cum 500 cum 1000 cum 1500 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest finish time ANSWER DOWNLOAD EXAMIANS APP