Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

None of these
expected time of activity B is greater than the expected time of activity A
expected time of activity A is greater than the expected time of activity B
expected time of both activities A and B are same

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

All listed here
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

ANSWER DOWNLOAD EXAMIANS APP