Construction Planning and Management
Mobilization advance up to 10% of the cost of work is given to a contractor

For all activities required to start the work at site on finalization of the contract document
For the purchase of construction materials
On commencement of work at site for payment of loan taken by him
For the payment of advances to labour and other staff

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Crash project duration is obtained by summing the

Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Normal durations for all the activities

ANSWER DOWNLOAD EXAMIANS APP