Construction Planning and Management Various activities of a project, are shown on bar charts by Crosses Dots Vertical lines Horizontal lines Crosses Dots Vertical lines Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 1500 cum 1000 cum 2000 cum 500 cum 1500 cum 1000 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 9 days 19 days 14 days 13 days 9 days 19 days 14 days 13 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Duration Interfering float Free float Total float Duration Interfering float Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Avoids delays which are very common in bar charts All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method Avoids delays which are very common in bar charts All listed here Provides a realistic approach to daily problems Is an improvement upon bar chart method ANSWER DOWNLOAD EXAMIANS APP