Construction Planning and Management Various activities of a project, are shown on bar charts by Dots Crosses Horizontal lines Vertical lines Dots Crosses Horizontal lines Vertical lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For completion of a project, the critical path of the network represents Minimum cost Maximum time Maximum cost Minimum time Minimum cost Maximum time Maximum cost Minimum time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float Zero float Maximum float None of these Minimum float Zero float Maximum float None of these ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials Variation in total cost of the project on an ad hoc basis Variation in cost in materials element, labour element and petrol-oil-lubricant element Rate of inflation Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements:In the critical path method of construction planning, Free Float can be.1. Greater than Total Float.2. Greater than Independent Float3. Equal to Total Float.4. Less than Independent Float 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct 2 and 3 are correct 1 and 2 are correct 1 and 4 are correct 1 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the execution of a project, a contractor is An agency All listed here A person A firm An agency All listed here A person A firm ANSWER DOWNLOAD EXAMIANS APP