Construction Planning and Management Various activities of a project, are shown on bar charts by Dots Vertical lines Crosses Horizontal lines Dots Vertical lines Crosses Horizontal lines ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications All listed here Separation of planning and design part Each individual maintains functional efficiency Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Any project Major projects All listed here Minor projects Any project Major projects All listed here Minor projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The first stage of a construction, is Survey of the site Preparation of estimate Initiation of proposal Preparation of tender Survey of the site Preparation of estimate Initiation of proposal Preparation of tender ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 97.7% and 84.1% 97.7 % and 15.9% 2.3% and 84.1% 15.9% and 97.7% 97.7% and 84.1% 97.7 % and 15.9% 2.3% and 84.1% 15.9% and 97.7% ANSWER DOWNLOAD EXAMIANS APP