Construction Planning and Management Various activities of a project, are shown on bar charts by Vertical lines Crosses Horizontal lines Dots Vertical lines Crosses Horizontal lines Dots ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (i) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (ii) and (iii) are correct (i) and (iii) are correct (ii) and (iv) are correct (i) and (iv) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Minimum Zero Infinite Maximum Minimum Zero Infinite Maximum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 19 24 None of these 14 19 24 None of these 14 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be None of these Both resources and project duration time Project duration time Resources None of these Both resources and project duration time Project duration time Resources ANSWER DOWNLOAD EXAMIANS APP