Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time All listed here Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Whenever an activity has zero total float, then Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero Independent float must be zero but free float need not be zero Free float and independent float both must be zero Free float and independent float both need not be zero Free float of the activity must be zero but independent float need not be zero ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is Top level executions over work All listed here Rigid structure Extraordinary delay in communications Top level executions over work All listed here Rigid structure Extraordinary delay in communications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management During the construction period, price variation clause in contracts caters to Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials Rate of inflation Variation in cost in materials element, labour element and petrol-oil-lubricant element Variation in total cost of the project on an ad hoc basis Increase in rates of only important materials ANSWER DOWNLOAD EXAMIANS APP