Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

All listed here
Completed 5 days later
Performed at slower rate in 15 days
Started 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The reduction in project time normally results in

Decreasing the direct cost and indirect cost both
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and increasing indirect cost

ANSWER DOWNLOAD EXAMIANS APP