Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Started 5 days later
Completed 5 days later
All listed here
Performed at slower rate in 15 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All listed here

ANSWER DOWNLOAD EXAMIANS APP