Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Completed 5 days later
All listed here
Performed at slower rate in 15 days
Started 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

should invest in project A
should invest in project B
could invest in either of the two projects
should invest in neither of the two projects

ANSWER DOWNLOAD EXAMIANS APP