Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Started 5 days later
All listed here
Completed 5 days later
Performed at slower rate in 15 days

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All listed here
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Independent float must be zero but free float need not be zero
Free float and independent float both must be zero
Free float and independent float both need not be zero
Free float of the activity must be zero but independent float need not be zero

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
During the construction period, price variation clause in contracts caters to

Rate of inflation
Variation in cost in materials element, labour element and petrol-oil-lubricant element
Variation in total cost of the project on an ad hoc basis
Increase in rates of only important materials

ANSWER DOWNLOAD EXAMIANS APP