Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Batching refers to

Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Controlling the total quantity at each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch

ANSWER DOWNLOAD EXAMIANS APP