Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Performed at slower rate in 15 days
Completed 5 days later
Started 5 days later
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased.

A is false but R is true
Both A and R is true but R is not the correct explanation of A
A is true but R is false
Both A and R is true and R is the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP