Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main disadvantage of line organization, is All listed here Extraordinary delay in communications Top level executions over work Rigid structure All listed here Extraordinary delay in communications Top level executions over work Rigid structure ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be 7.87 years 3.7 years 5 years 4.23 years 7.87 years 3.7 years 5 years 4.23 years ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 Rs. 6960 Rs. 1740 Rs. 3480 Rs. 5220 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Free float for any activity is defined as the difference between its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity its latest finish time and earliest start time for its successor activity its latest start time and earliest start time its earliest finish time and earliest start time for its successor activity its earliest finish time and latest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct (ii) and (iv) are correct (ii) and (iii) are correct (i) and (iv) are correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP