Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here Completed 5 days later Started 5 days later Performed at slower rate in 15 days All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Slack time refers to An activity None of these Both event and activity An event An activity None of these Both event and activity An event ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 100% at the site 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement 100% at the site 33% at the site and 67% under procurement 67% at the site and 33% under procurement 50% at the site and 50% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg Reduce by 200 kg Reduce by 250 kg Increase by 200 kg Increase by 250 kg ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following excavators is most suitable for digging under water? Clam shell Drag line Hoe Dipper shovel Clam shell Drag line Hoe Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1920 1930 1910 1940 1920 1930 1910 ANSWER DOWNLOAD EXAMIANS APP