Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Economic saving of time results by crashing Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity Cheapest critical activity Costliest noncritical activity Cheapest noncritical activity Costliest critical activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following is not an excavating and moving type of equipment? Scraper Clam shell Bulldozer Dump truck Scraper Clam shell Bulldozer Dump truck ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The salient feature of functional organization is Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications Separation of planning and design part Each individual maintains functional efficiency All listed here Strict adherence to specifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 14 None of these 19 24 14 None of these 19 24 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is 16 days 4 days 6 days 10 days 16 days 4 days 6 days 10 days ANSWER DOWNLOAD EXAMIANS APP