Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Performed at slower rate in 15 days
Started 5 days later
All listed here
Completed 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
A part of the money kept in reserve for providing additional structures and structural modifications
The total sum to be paid to the municipal authorities by the tenants

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

None of these
expected time of both activities A and B are same
expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A

ANSWER DOWNLOAD EXAMIANS APP