Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Minimum Zero Maximum Infinite Minimum Zero Maximum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1910 1930 1920 1940 1910 1930 1920 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Wheeled tractors are replacing crawler tractors because1. Wheeled tractors travel faster.2. Crawler tractors are more expensive.3. Track parts of a crawler wear out quickly.4. Crawler tractors have stick control.of following statements 1, 2 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct 1, 2 and 4 are correct 1, 3 and 4 are correct 1, 2 and 3 are correct 2, 3 and 4 are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For a given size of bucket, the ideal output of a dragline will be least in Sand and gravel Wet sticky clay Good common earth Moist loam Sand and gravel Wet sticky clay Good common earth Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these activities is 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 3, 1, 2, 4 1, 3, 4, 2 1, 3, 2, 4 3, 1, 4, 2 ANSWER DOWNLOAD EXAMIANS APP