Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The area under the Beta distribution curve is divided into two equal parts by Most likely time Optimistic time Pessimistic time Expected time Most likely time Optimistic time Pessimistic time Expected time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Delegation of authority All listed here Effective control at all levels Unity of command Delegation of authority All listed here Effective control at all levels Unity of command ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following is not a PERT event? Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started Sessional work completed Bus starts from Jaipur Class is being attended Site investigation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management CPM is All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts All listed here Is based on time estimate Is built of activities oriented programme Synthesising in concepts ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Residential buildings are treated as Industrial construction Heavy construction Light construction Private construction Industrial construction Heavy construction Light construction Private construction ANSWER DOWNLOAD EXAMIANS APP