Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be 20.143 minutes 27 minutes 15 minutes 21 minutes 20.143 minutes 27 minutes 15 minutes 21 minutes ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 500 cum 2000 cum 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The main principle of an organization, is Unity of command All listed here Delegation of authority Effective control at all levels Unity of command All listed here Delegation of authority Effective control at all levels ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For excavating utility trenches with precise control of depth, the excavation equipment used is Hoe None of these Dragline Shovel Hoe None of these Dragline Shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Zero float Maximum float Minimum float None of these Zero float Maximum float Minimum float None of these ANSWER DOWNLOAD EXAMIANS APP