Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Performed at slower rate in 15 days
Started 5 days later
All listed here
Completed 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Whenever an activity has zero total float, then

Free float and independent float both need not be zero
Free float and independent float both must be zero
Free float of the activity must be zero but independent float need not be zero
Independent float must be zero but free float need not be zero

ANSWER DOWNLOAD EXAMIANS APP