Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

All listed here
Started 5 days later
Performed at slower rate in 15 days
Completed 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
At a work site, statistical quality control of concrete means

Reduction in wastage of inspection costs
Applying the theory' of probability to sample testing or inspection
Measurement of risks to eliminate failures
Reduction in costs for the removal of defects

ANSWER DOWNLOAD EXAMIANS APP