Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Constraint Dummy Event Free float Constraint Dummy Event Free float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path method Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here Is an improvement upon bar chart method Avoids delays which are very common in bar charts Provides a realistic approach to daily problems All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Military organization is known as None of these Line organization Functional organization Line and staff organization None of these Line organization Functional organization Line and staff organization ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here Initiating the procurement action of resources Preparation of estimates Preparation of specifications All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Equal to X More than X Less than X Any of the above Equal to X More than X Less than X Any of the above ANSWER DOWNLOAD EXAMIANS APP