Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Performed at slower rate in 15 days
Completed 5 days later
All listed here
Started 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

Raised to meet maintenance costs
A part of the money kept in reserve for providing additional structures and structural modifications
The fund for rebuilding a structure when its economic life is over
The total sum to be paid to the municipal authorities by the tenants

ANSWER DOWNLOAD EXAMIANS APP