Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sensitivity analysis is a study of Change in output due to change in input Comparison of profit and loss Comparison of assets and liabilities Economics of cost and benefits of the project Change in output due to change in input Comparison of profit and loss Comparison of assets and liabilities Economics of cost and benefits of the project ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Works costing less than Rs. 20,000 are treated as Major projects Any project Minor projects All listed here Major projects Any project Minor projects All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Updating may result in Change of critical path All of these Increase of project completion time Decrease of project completion time Change of critical path All of these Increase of project completion time Decrease of project completion time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 1, 3 and 4 1, 2 and 4 1, 2 and 5 3, 4 and 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In the given figure, the network of a project represents Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing Activity of excavation which takes 8 units of time Activity of an excavation which starts at event No. 1 and ends at even No. 2 None of these Activity of an excavation of a footing ANSWER DOWNLOAD EXAMIANS APP