Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later Completed 5 days later All listed here Performed at slower rate in 15 days Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the output of a drag-line for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be Less than X More than X Equal to X Any of the above Less than X More than X Equal to X Any of the above ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in project A should invest in project B could invest in either of the two projects should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects should invest in neither of the two projects ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% 15.9% and 97.7% 97.7 % and 15.9% 2.3% and 84.1% 97.7% and 84.1% ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A construction schedule is prepared after collecting Output of machinery Number of operations Output of labour All listed here Output of machinery Number of operations Output of labour All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Railway projects are treated as Light construction None of these Heavy construction Industrial construction Light construction None of these Heavy construction Industrial construction ANSWER DOWNLOAD EXAMIANS APP