Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days All listed here Started 5 days later Completed 5 days later Performed at slower rate in 15 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For which of the following materials, the output of power shovels for a fixed shovel size will be maximum Well blasted rock Wet sticky clay Good common earth Moist loam Well blasted rock Wet sticky clay Good common earth Moist loam ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following earth moving machines has the shortest cycle time? Clam shell Hoe Drag line Dipper shovel Clam shell Hoe Drag line Dipper shovel ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Zero Maximum Infinite Minimum Zero Maximum Infinite Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Time and progress chart of a construction, is also known as Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct A is correct but R is not correct Both A and R is incorrect Both A and R is correct R is correct but A is not correct ANSWER DOWNLOAD EXAMIANS APP