Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: All listed here Laying of concrete started Digging of foundation completed Digging of foundation started All listed here Laying of concrete started Digging of foundation completed Digging of foundation started ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. A is false but R is true Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A A is false but R is true Both A and R is true but R is not the correct explanation of A A is true but R is false Both A and R is true and R is the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Mile Stone charts were invented in the year of 1940 1920 1930 1910 1940 1920 1930 1910 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Curing of concrete Excavation for foundation Setting of question paper All listed here Curing of concrete Excavation for foundation Setting of question paper All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 (a + m + b)/6 (a + 5m + b)/6 (a + 4m + b)/6 (a + 2m + b)/6 ANSWER DOWNLOAD EXAMIANS APP