Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here Completed 5 days later Performed at slower rate in 15 days Started 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good LF = LS + D All listed here EF = ES + D LS = LF - D LF = LS + D All listed here EF = ES + D LS = LF - D ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In time-cost optimization of a project, crashing is done. Only on activities lying on the original critical path and having flatter cost slopes On all the activities On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope Only on activities lying on the original critical path and having flatter cost slopes On all the activities On all the activities lying on the critical path On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Maximum Infinite Zero Minimum Maximum Infinite Zero Minimum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Sinking fund is The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications The fund for rebuilding a structure when its economic life is over Raised to meet maintenance costs The total sum to be paid to the municipal authorities by the tenants A part of the money kept in reserve for providing additional structures and structural modifications ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP