Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Completed 5 days later
Started 5 days later
All listed here
Performed at slower rate in 15 days

ANSWER DOWNLOAD EXAMIANS APP