Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

None of these
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
expected time of activity A is greater than the expected time of activity B

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Latest start of an activity is always

equal to latest event time of preceding node
greater than or equal to latest event time of preceding node
less than latest event time of preceding node
less than or equal to latest event time of preceding node

ANSWER DOWNLOAD EXAMIANS APP