Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Completed 5 days later
Performed at slower rate in 15 days
Started 5 days later
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In time-cost optimization of a project, crashing is done.

Only on activities lying on the original critical path and having flatter cost slopes
On all the activities
On all the activities lying on the critical path
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Sinking fund is

The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications

ANSWER DOWNLOAD EXAMIANS APP