Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The critical activity has Minimum float Zero float None of these Maximum float Minimum float Zero float None of these Maximum float ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management What estimate would you give for the variance in above problem ? 81 9 54 36 81 9 54 36 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum 500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management For the network shown in the given figure, the expected time for the activity 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 2-3 is 7 1-2 is 4 All listed here 3-4 is 8 ANSWER DOWNLOAD EXAMIANS APP