Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Completed 5 days later
All listed here
Performed at slower rate in 15 days
Started 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Output of a bulldozer is(i) Increased if drawbar HP of the tractor is increased for a given hauling distance(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor

(i) and (iv) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
(i) and (iii) are correct

ANSWER DOWNLOAD EXAMIANS APP