Construction Planning and Management
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

Performed at slower rate in 15 days
Completed 5 days later
All listed here
Started 5 days later

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Total float for any activity is defined as the difference between

Its latest start time and earliest start time
Its latest start time and earliest finish time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and earliest start time for its successor activity

ANSWER DOWNLOAD EXAMIANS APP